TM 5-2420-224-20-2
CRANE REPLACEMENT (CONT)
9.
10.
11.
12.
START ENGINE, EXTEND tilt CYLINDER (9)
to aline with mounting eye, and ENGAGE
crane LOCKS.
CONNECT tilt CYLINDER (9) and INSTALL tilt
cylinder PIN (10) and two snap rings (11).
INSTALL pivot PIN (12) and two snap rings
(13) on left side crane mounting.
INSTALL pivot PIN (14) and two snap rings
(15) on right side crane mounting.
13. INSTALL BOX (4) and four screws (3).
14. INSTALL two WIRES (2) and two nuts (1)
and CAREFULLY ROLL rubber BOOTS OVER
connection.
NOTE
Follow-on Maintenance:
Install rear composite stoplight/
taillight (driver side) (page 4-190).
Install work light (page 4-186).
4-782