TM 11-7440-278-14
CHAPTER 4
OPERATOR AND ORGANIZATIONAL MAINTENANCE INSTRUCTIONS
NOTE
No operator crew maintenance has been authorized for the AN/MYK-8(V) (.").
Section I.
TOOLS AND EQUIPMENT
4-1.
Common Tools and Equipment
4-2.
Special Tools and Equipment
Refer to appendix D, section III of this manual for a list of
No special tools or equipment are required for servicing
tools and equipment authorized for use by organizational
the AN/MYK-8 (V) (*).
maintenance.
Section II.
REPAINTING, REFINISHING AND LUBRICATION INSTRUCTIONS
caution notice.
CAUTION
Solar reflecting paint per MIILE-
46061A(MO has been used to paint the
4-3.
Repainting and Refinishing
exterior of some AN/MYK-8(V) (*)
To touch up the assemblages, remove paint rust and
assemblage facilities to lower the inside
corrosion from metal surfaces by lightly sanding surfaces
temperature during exposure to the
with fine sandpaper. Brush two coats of paint (one
direct rays of the sun.
However,
primer and one final) on bare metal to protect it from
camouflage paint has been used to paint
further corrosion.
the exterior of tactical units. Before
doing any touchup) painting on the
4-4.
Lubrication requirements for the AN/MYK-
exterior of any assemblage, check for
8(V)(*) assemblage are those described in the
any caution notices on the entrance
pertinent lubrication orders listed in appendix A of
door. Do not use any paint other than
this manual
specified
by
the
Section III. PREVENTIVE MAINTENANCE CHECKS AND SERVICES
for corrective action.
4-5.
General
To ensure that the assemblages of the AN/MYK-8(V) (*)
4-6.
Instructions for the Performance of Pre-
are always ready for operation, they must be inspected
systematically to discover and correct defects before
ventive Maintenance Checks and Services
they result in serious dam-age or failure. The necessary
The items listed in table 4-1 should be inspected on a
preventive maintenance checks and services are listed
weekly basis.
and prescribed in table 4-1. The item numbers indicate
NOTE
the sequence of minimum inspection requirements.
The preventive maintenance schedule
Defects discovered during operation of the assemblage
for the ADP equipment is arranged
Mill be noted for future correction as soon as operation
between the using organization and the
has ceased. Stop operation immediately if a deficiency
concerned IBM field engineering staff.
is noted during operation that would damage the
The schedule is tailored to meet system
equipment. Record all deficiencies and report to the IBM
requirements as determined by system
field engineering staff
history, usage, and peak loads.
4-1